Delivering operational excellence Jan Moström, President Boliden Mines Capital Markets Day 2014 10 November 2014

CMD 2014

42

2014-11-10

Delivering operational excellence

Operational excellence

Productivity - availability Metallurgy Tara transformation Project management

Organic expansion

Focusing on profitable growth M&A

CMD 2014

43

2014-11-10

Environmental excellence is a key focus 

Water treatment ‒ Fenton ‒ Biological process for nitrogen removal



Reclamation ‒ Tailings facilities ‒ Waste rock ‒ Sites



TMF, Operational performance

CMD 2014

44

2014-11-10

Acid mine water – oxidation of Pyrite

Pyrite Sulfide ore

CMD 2014

45

2014-11-10

High level of productivity but more to be achieved Copper - open pit with mill 2014

Zinc - underground mines 2016 tonne per man hour

5.0 4.5

tonne per man hour

35

Citronen project (Grönland)

Aitik

30

4.0 3.5

25

Garpenberg

3.0

Pyhäsalmi (Finland)

2.5 2.0

777 (Kanada) Doe Run (USA)

Bolidenområdet

Tara

Aguas Tenidas (Spanien) Tayahua Project (Mexiko) Cerro Lindo (Peru) Kazakhmys (Kazahstan)

1.5 1.0 0.5 0.0 0

1

2

3

4

5

Mineral Park (USA)

Gibraltar (Kanada) Boddington Butte (USA) (Australien)

20

Highland Valley Sierrita (USA) (Kanada)

15

Bingham Canyon (USA) Antamina (Peru) Cerro Verde (Peru) Los Pelambres

10 5

(Chile) Collahuasi (Chile)

Escondida (Chile)

0 0

6

20

40

60

80

Million tonne ore production per year

Million tonne ore production per year

CMD 2014

Mount Milligan (Kanada)

46

2014-11-10 5

100

Aitik – no 1 productivity Open pit Cu mines

Percentile **

Head grade

% Cu

99

Mine

t ore/hour

1

Mill

t ore/hour

0

G&A

t ore/hour

0

Overall

t ore/hour

0

Wage rate

$/hour

87

Labour cost

$/t

12

Cash cost, Normal C1* - All mines

c/lb Cu

42

* Cash cost Normal C1, Wood Mackenzie Q3 2014 estimate for 2014 ** All mines in Woodmackenzie model, Q2 2014 estimates for 2014 CMD 2014

47

2014-11-10

World-class design



Fundamentals ‒ ‒ ‒



Mine ‒



Geological target, conceptual study Mineral resource, pre feasibility Mineral reserve, feasibility study

Interaction infrastructure – production areas – stopes

Concentrator ‒ ‒ ‒ ‒

CMD 2014

Mill Flotation Dewatering TMF

48

2014-11-10

Increasing performance at mine and mill



Key productivity drivers at mine Minimizing lead time between work processes at faces/stopes/benches



Key drivers for the concentrator Optimizing availability of mill/flotation/dewatering and metallurgical performance

CMD 2014

49

2014-11-10

Integrated control system drives efficiency



Integrated control system for mine and mill ‒ Increased efficiency ‒ Lower costs



Mobile control room ‒ Enables operators to monitor and adjust in real time



Control system integrated with maintenance system ‒ Only one original document

‒ All share same info ‒ Improved surveillance ‒ Easier to spot errors ‒ Diary improves visibility over time



WLan ‒ Enable status control and operational guidance

CMD 2014

50

2014-11-10

Wlan Enable status control and operational guidance

CMD 2014

51

2014-11-10

Leading expertise in handling complex ore



90 years of mining complex ore



Complex deposits with increasing grades of penalty elements



Case: Kankberg

CMD 2014

Kylylahti Cu, Au, Zn, Ni, Co

52

2014-11-10

Patented process with high recoveries Kankberg – leaching of gold and tellurium from goldtellurides 

Conceptual study initiated 2008 ‒ Conventional leaching plant, method not an option ‒ A hot leaching process developed ‒ Boliden patent ‒ Gold recovery 85% (without 45%)

‒ Tellurium leaching process developed ‒ Tellurium recovery 65%



New process commissioned 2011

CMD 2014

53

2014-11-10

Restructuring Tara for improved profitability

Decrease mobile fleet Optimization on-going

Lowering headcount 2013 2014 Q3 2015

CMD 2014

700 620 590

54

2014-11-10

Future growth based on solid project pipeline Future options

Conceptual study

Pre feasibility study

feasibility study

execution

Aitik 45 Laver Garpenberg 2,5

Cu

Projects may loop, may be rejected or may be executed due to market conditions and project conditions

CMD 2014

55

Zn Au

2014-11-10

In-house project management a success factor 

General design by in-house resources



Project management all disciplines with in-house personnel



Suppliers used in parts of the project but no large turn-key assignments



Standardized process - Project manual with continuous improvements from previous projects A36. BoRe, Garpen, A45.



Key individuals assures continuity and experience sharing

Conceptual Study

CMD 2014

Prefeasibility Study

Feasibility study

56

Implementation

2014-11-10

Garpenberg – Set for 2.5 Mtonnes

CMD 2014

57

2014-11-10

Aitik45 

45 (38) mton annually, +20%



Reserve grade 0.22 (0.24) ‒ Reserves 1 085 (633) mtonnes ‒ Life of mine 2040 (2030) years ‒ Copper life of mine 2 348 (1 471) ktonnes



Capex ‒ New crushers with improved reliability ‒ Lower stripping, approx. 0.5 ‒ TMF



-10% costs per ton of ore ‒ Economies of scales



New environmental permit ‒ In all, in according to our application

CMD 2014

58

2014-11-10

Managing pushbacks to optimize financial performance

Ö

Sa2

CMD 2014

59

2014-11-10

Adjusted mine plan Aitik



New environmental permit fall 2014



45 Mton 2017



Production 2015, 40 Mton



Life of mine Cu grade unchanged 0.22%



Cu grade 2015 and 2016 0.21%



2017-2019 over average grade

CMD 2014

60

2014-11-10

Increased production with new crusher Improved reliability – proven design

Existing with reinforcements CMD 2014

New

61

2014-11-10

Further growth options Laver 

Kylylahti ‒ Near mine ‒ Depth ‒ Satelites

‒ Outokumpu Field



Laver ‒ Application for mine concession Q3 2014 ‒ Next step, pre feasibility

CMD 2014

62

2014-11-10

Exploration, an unique opportunity

”Malmfälten”

Skellefte field

Outokumpu field

Bergslagen

CMD 2014

63

2014-11-10

Kylylahti – near mine exploration

CMD 2014

64

2014-11-10

Outokumpu Area – Copper and Nickel Deposits

Kokka

Luikonlahti

Saramäki

Kylylahti Perttilahti Vuonos Riihilahti

CMD 2014

Keretti Hautalampi

65

2014-11-10

Delivering operational excellence

Operational excellence

Productivity - availability Metallurgy Tara transformation Project management

Organic expansion

Focusing on profitable growth M&A

CMD 2014

66

2014-11-10

Disclaimer 

This presentation has been prepared by Boliden for information purposes only and as per the indicated date. Boliden does not undertake any obligation to correct or update the information or any statements made therein. Certain statements in this presentation are forward-looking and are subject to risks and uncertainties.



Nothing contained herein shall constitute any representation or warranty as to accuracy or completeness. Boliden has not made any independent verification of the information obtained from third parties.



Nothing in this material shall be construed as an offer or solicitation to buy or sell any security or product, or to engage in or refrain from engaging in any transaction.



Boliden does not accept any liability whatsoever arising from or in connection with the use of this information.



Save as by prior approval in writing, this material may not be copied, transmitted or disclosed, whether in print, electronic or any other format. All rights to the material are reserved.

CMD 2014

2014-11-10

Capital Markets Day 90 years of knowledge delivering today’s value